What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

With support from Rappahannock Electric Cooperative (REC) and funding through The Power of Change, a new chapter in affordable housing began Tuesday, ...
When the 2025 Walk for Mental Wellness stepped off in downtown Fredericksburg, one group among the crowd stood out – not just for their #WeAreREC shir...
The funding supports underserved populations through a diversity of projects including food insecurity, housing and shelter assistance, health and edu...