What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

Jaylin Margerum is a high school senior who plans to make trades a career. Girl Power Camp practically sold her on it. Margerum was one of 49 young wo...

Understanding Today’s Energy Costs

Wednesday | January 7, 2026
Affordability is top of mind for many, including REC member-owners. Why are energy costs increasing? How is REC keeping costs down? Hear from REC Pres...

Keeping Cozy for Less

Wednesday | January 7, 2026
With a few strategic adjustments and smart habits, you can maintain a cozy home while managing your energy use and costs.