What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

REC was recently celebrated for its commitment to youth empowerment, receiving the 2024 Thomas G. Faulkner, Jr. Award from Big Brothers Big Sisters of...
REC has named Steven Roddy as Chief Financial Officer (CFO). In this role, Roddy is responsible for developing financial strategies, overseeing budget...
REC has hired Benjamin Chang as the Cooperative’s Director – Hyperscale Infrastructure Projects. In his new role, Chang is the principal executive lea...