What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

Due to the generosity of over 30,000 REC member-owners, 22 local organizations were recently awarded grants totaling nearly $93,000. 
Is now the right time to purchase an electric vehicle? How far can you drive on a full charge? How does charging work, anyway? Will an electric vehicl...

REC Helps Sponsor First Girl Power Camp

Friday | September 24, 2021
Eleven high school girls got a taste of what it’s like to be an electric utility lineworker at the first Girl Power Camp, sponsored by the Virginia, M...