The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

REC announces its partnership in the “Connect Hannover” initiative with Hanover County, All Points Broadband and Dominion Energy to make broadband ser...
Some REC member-owners in Louisa County are one step closer to having access to broadband internet service.

Prepare Now for Tropical Storm Elsa

Wednesday | July 7, 2021
Heavy rain and wind gusts up to 40 mph could impact much of Virginia beginning Thursday evening and continuing into Friday as Tropical Storm Elsa pass...