Solar generation facility
Solar Solutions

Small Generator
Interconnection

Learn about the process for connecting a small generating facility to REC's electric system.

Getting Started

What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional interconnection requests are categorized into three separate processes in the regulations.

Review Chapter 314

Interconnection Levels

The appropriate process depends on the size and qualification of the small generating facility.

1
Level 1

Up to 500 kW

Certified SGF

A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

2
Level 2

Up to 2 MW

Certified SGF

A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

3
Level 3

Other SGFs

Additional Review

A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

Virginia Interconnection Regulations

Review the complete Regulations Governing Interconnection of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

REC STORIES

REC crews and contractors continue the grueling task of making repairs and restoring service after the devastating impact of Winter Storm Frida.
REC crews and contractors continue to assess damage, make repairs and restore service after historic Winter Storm Frida toppled trees, downed power li...
REC took a direct hit today from Winter Storm Frida, which downed power lines, toppled trees and knocked out power to more than 90,000 member-owners a...