Solar generation facility
Solar Solutions

Small Generator
Interconnection

Learn about the process for connecting a small generating facility to REC's electric system.

Getting Started

What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional interconnection requests are categorized into three separate processes in the regulations.

Review Chapter 314

Interconnection Levels

The appropriate process depends on the size and qualification of the small generating facility.

1
Level 1

Up to 500 kW

Certified SGF

A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

2
Level 2

Up to 2 MW

Certified SGF

A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

3
Level 3

Other SGFs

Additional Review

A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

Virginia Interconnection Regulations

Review the complete Regulations Governing Interconnection of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

REC STORIES

REC's bucket trucks are big – so big that at the Middletown Christmas Parade, it was carrying a child size gingerbread house!
Already bright yellow, REC bucket truck stood out at the Culpeper Christmas Parade as it was decked out with lights, a snowman and Christmas tree.
REC employees joined the holiday fun at the Clarke County Christmas Parade on Dec. 4.