Solar generation facility
Solar Solutions

Small Generator
Interconnection

Learn about the process for connecting a small generating facility to REC's electric system.

Getting Started

What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional interconnection requests are categorized into three separate processes in the regulations.

Review Chapter 314

Interconnection Levels

The appropriate process depends on the size and qualification of the small generating facility.

1
Level 1

Up to 500 kW

Certified SGF

A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

2
Level 2

Up to 2 MW

Certified SGF

A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

3
Level 3

Other SGFs

Additional Review

A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

Virginia Interconnection Regulations

Review the complete Regulations Governing Interconnection of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

REC STORIES

On Tuesday, June 25, REC was honored as Chamber Partner of the Year at the Louisa County Chamber of Commerce’s Annual Meeting.
On the evening of June 26, REC hosted a live Telephone Town Hall, giving thousands of members the opportunity to hear directly from REC President and ...
REC is proud to announce that it has awarded $20,000 in scholarships to 17 outstanding students across its service territory.