What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

REC Recognized for Strong Customer Satisfaction

Thursday | September 26, 2024
REC members have spoken, and as a result the Cooperative and its employees earned both a 2023 and a 2024 Customer Satisfaction Award from the American...
Over the summer, REC’s Vegetation Management team supported the Virginia State Arboretum’s initiative to pollinate American chestnut trees at Blandy E...

REC Warns of In-Person Impersonation Scams

Friday | September 20, 2024
REC has seen an increase in potential in-person scams in the southeast portion of its service area.