What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

REC at the Career Fair

Saturday | October 28, 2023
REC employees talked with students at career days in Greene and Caroline counties.

REC Joins the 2023 Jack-O-Lantern Jubilee

Friday | October 27, 2023
REC employees passed out candy to princesses, witches, ghosts and ghouls alike at the Warren County DSS Jack-O-Lantern Jubilee on Oct. 26. 
For over an hour, on Thursday evening member-owners of Rappahannock Electric Cooperative (REC) participated in a question and answer discussion direct...