What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

REC Sponsors Annual Holiday Writing Contest

Saturday | December 10, 2022
On Dec. 8 the Samuels Library in Front Royal held their 44th Holiday Writing Contest.

REC Powers Fort A.P. Hill Tree Lighting

Thursday | December 8, 2022
On Tuesday, Dec. 6, REC employees engaged with families and employees at Fort A.P. Hill for their tree lighting festivities.
REC employees enjoyed spreading the holiday cheer at three local Christmas parades in the Blue Ridge region.