What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

REC linemen brought a bucket truck and talked to children about electrical safety at the Fall Festival at Wilderness Baptist Church.
REC participated in the first Headwaters Harvest Festival at Eldon Farms in Woodville on Saturday, Oct. 1.

REC Reminds Members of Storm Prep Importance

Wednesday | September 28, 2022
REC is closely monitoring the storm track for Hurricane Ian, as it gets closer to landfall in the Southeast. The Cooperative’s thoughts are with the r...