What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

REC employees attended the disAbility Resource Center’s 2023 Fall Festival.

REC at the Shen Valley Apple Harvest Festival

Tuesday | September 19, 2023
REC employees had a blast connecting with the community at the Shenandoah Apple Harvest Festival in the heart of the Shenandoah Valley.

REC Wraps Up the 2023 Farmer's Market Season

Monday | September 18, 2023
The season of Farmers Markets wrapped up, keeping employees busy with connecting with members.