What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

For questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

Putting the WoW Factor in Career Expo

Sunday | September 17, 2023
Apprentice Linemen Kevin Ryan and Hunter Jost met with students at the Worlds of Work (WoW) career expo to share about their job and responsibilities ...

2023 Louisa Biz Expo

Saturday | September 16, 2023
Hosted by the Louisa Chamber of Commerce, the Louisa Biz Expo provides businesses the opportunity to connect with others and the community.
Matt Fauver spent more than a decade suiting up in lineman gear, upgrading electrical equipment in the field and restoring outages after storms rolled...