What Members Should Know

The Small Generator Interconnection process on REC's system follows the State jurisdictional Regulations Governing Interconnections of Small Electrical Generators and Storage in Chapter 314 of the Virginia Administrative Code.

State jurisdictional Interconnection requests are categorized into three separate processes in the regulations.

Level 1 – A request to interconnect a certified small generating facility (SGF) no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

Level 2 – A request to interconnect a certified SGF no larger than 2 MW and not qualifying for the Level 1 process shall be evaluated under the Level 2 process.

Level 3 – A request to interconnect an SGF not qualifying for the Level 1 process or Level 2 process shall be evaluated under the Level 3 process.

To view the Rappahannock Interconnection Queue and Frequently Asked Questions, please visit the Virgina Small Generation Interconnection Portal here

For all other questions regarding the Small Generator Interconnection Process, please contact us at RECSGIRequest@myrec.coop.

To submit a Small Generator Interconnection Application, please use Schedule 6 of the Virginia Administrative Code 314 located here.

Small Generator pic with solar panels

REC STORIES

REC is pleased to announce that Brian Baer and Rachel Lugo have earned recognition as professional communicators in a national certification program o...

REC Promotes Local Trades

Saturday | January 27, 2024
REC employees talked with high school CTE students about the career path of different trades.

REC Attends 2024 Co-op Legislative Day

Thursday | January 25, 2024
Tuesday, Jan. 23 was the annual Co-op Legislative Day.